GENERAL RISK ASSESSMENT AND CONTROLS

 

Job Title

Location & Production area

No. Of Personnel in area

HAZARD
What are the hazards in this area?

 

RISK
Is the hazard likely to cause harm or or damage to property and why?

 

Are control measures in use and what are they?
Level of Risk
STOP
Imminent Danger
CAUTION
Level of risk unacceptable improvement required within 4 months
IMPROVE
Level of risk needs to be reduced within 12 months
or by agreement
ACCEPT
Review after 2 years
What action is required and by whom?
 