Supervisors Weekly
Self-Inspection Checklist
This must be completed each week
as a requirement of our insurance cover

 

The overall objective is prevention of fire.

Name of company :-
Building or department reference:-
1. HEATING :-
Boilers
Are the required safety checks carried out and recorded?YesNo
Are fusible link cut offs operative ? YesNo
Space Heaters
Are fusible link devices operative? YesNo
Is stock and/or work in progress at least 1 metre from the heater?YesNo
Portable Heaters
Portable heaters should not be used without prior approval.
Oil Tanks
All oil tanks should be bunded ( catchpit) YesNo
Are the bunds clear of debris? YesNo
Are drain valves fitted to remove waste liquids?YesNo
Are the valves on the oil tanks locked off to prevent tampering?YesNo
LPG Storage Tanks
Are they fenced off?YesNo
Is the tank earthed?YesNo
Are earthing clips available?YesNo

If any of the above were answered NO please state action taken.


2. SMOKING
Are smoking rules observed?YesNo
Where smoking is allowed , are there sufficient receptacles? YesNo
Are they used?YesNo
3. MAINTENANCE/ENGINEERS
Flammable liquids
Are flammable liquids stored in fire resisting cabinets /bins? YesNo
Are approved containers in use? YesNo
Are all flammable liquids returned to store at the end of the shift? YesNo
Are lidded metal bins provided for waste material? YesNo
Gases 
Are all cylinders properly secured in the work place? YesNo
Is a locked compound provided for storage?YesNo
Are LPG cylinders separated from the rest?YesNo
Are spark arrestors fitted on cutting equipment?YesNo
Is the Hot Work permit observed?YesNo
Is ammonia detection provided and working?YesNo
4. SECURITY
Are fences and gates in good condition
with no damage creating access points?
YesNo
Are gates locked or manned out of hours?YesNo
Are all windows, doors locked out of hours?YesNo
Are doors to storage areas, packaging stores and dry goods
kept closed at all times as a matter of policy?
YesNo
Is the intruder alarm working and 'on' out of hours?YesNo
If any of the above were answered NO please state action taken.

 

 

5. HOUSEKEEPING
Internal
Are storage areas tidy with no stock on the floor obstructing aisles? YesNo
Is stock clear of electrical equipment , heaters and battery chargers? YesNo
Is all waste removed outside the buildings daily? YesNo
External
Are waste bins and skips tidy and secure against tampering? YesNo
Are waste skips at least 10 metres away from buildings? YesNo
Are pallets stored at a least 10 metres from external building walls YesNo
Are canopies , loading bays and lean-to areas clear of stock ( other than that being immediately taken in or out of the buildings). YesNo
6. ELECTRICS
Are switch rooms locked and secure?YesNo
Are switch rooms clear of all non related materials?YesNo
Are switch boards kept clear of stock? YesNo
Are there any trailing leads, temporary wiring that require attention?YesNo
7. PROCESS
Ovens
Are maintenance schedules being observed? YesNo
Are extract ducts and oven beds cleaned on a regular cycle?YesNo
Fryers
Are maintenance procedures and schedules observed and up to date?YesNo
Are overheat warning sytems operative ? YesNo
Are extraction ducts and filters cleaned on a regular cycle?YesNo
Is fixed fire protection on a maintenance contract? YesNo
Are fire protection systems indicating healthy?  YesNo
Are there any ovens or fryers within 3 metres of wall or ceiling panels constructed of polystyrene or polyurethane. Such materials should be replaced by approved construction material or over clad with fire resisting material.YesNo
Kitchens
Are filters over cooking equipment particularly fryers cleaned or replaced on an acceptable frequency?YesNo
Are first aid fire appliances provided ?YesNo
If any of the above were answered NO please state action taken.

 

 

8. PREMISES
Is there any damage to wall and ceiling panels?
Any such damage should be repaired promptly.
YesNo

Are roof spaces clear of all unnecessary materials?

YesNo
Is there any exposed polystyrene requiring capping?YesNo
Is all packing material stored in a tidy fashion?YesNo
9. FIRE PROTECTION
Alarm
Is the fire alarm panel indicating healthy? YesNo
Are the panel lamps all working? YesNo
Is any signalling to central station or gatehouse operative?YesNo
Extinguishers
All available and accessible? YesNo
Hose Reels
Maintenance contracts in force and up to date? YesNo
Location notices provided? YesNo
Nozzles present on hose reels? YesNo
Fire Doors
Self closing devices working?YesNo
Doors not obstructed?YesNo
Sprinklers  where appropriate.
Weekly alarm test carried out? YesNo
Pump tested weekly? YesNo
Test card marked up to date? YesNo
Valves strapped and padlocked? YesNo
If any of the above were answered NO please state action taken.

 

 

Completed by ...................................................

Position ...................................................

Date ....

Signature of Site Director

 
  